Wade Utility Plant Boiler No. 7 Infrastructure Preparation
Location: Purdue University, West Lafayette, IN
Client: Purdue University
Completion: 2011
Value: $1.1M
Highlights:
- Required complex scheduling and coordination while maintaining critical operations on campus
- Earned an Exceptional performance rating from client.
Coordination with Multiple Contractors
CMS was required to prepare a mechanical infrastructure to accept equipment from a separate contractor. After flagging possible areas of incompatibility in the RFP, CMS contacted the equipment provider and worked closely with them in order to provide a perfect match between the infrastructure we built and the equipment they installed.
Scope
This project consisted of furnishing, installing and placing in successful operation a new steam generating facility infrastructure in which new steam equipment would be provided to generate and dispense steam throughout the University campus. CMS was contracted to provide a full and complete infrastructure to accept the 200,000 lbs/hr natural gas fired package boiler, and also to fabricate piping to fit the new system.